Caledonia Mining Corporation Plc (“Caledonia” or the “Company” – https://www.youtube.com/watch?v=7aQP-cMNrOI) announces its operating and financial results for the fourth quarter (“Q4” or the “Quarter”) and the year ended December 31, 2017 (the “Year”). Caledonia’s primary asset is a 49 per cent legal ownership in the Blanket Mine (“Blanket”) in Zimbabwe. Caledonia continues to consolidate Blanket and the operational and financial information set out below is on a 100 per cent basis unless indicated otherwise.

Steve Curtis, Chief Executive Officer, said:

I’m delighted to report that production for the year was a new record: the 56,133 ounces of gold produced in 2017 being 11.5 per cent higher than in 2016. The production difficulties which we encountered in the first half of the year were identified and addressed and it was pleasing to see that these remedial measures resulted in Blanket achieving consecutive production records in the third and fourth quarters of the year.

“In addition to increased production, we have also reduced our unit costs:  Caledonia’s AISC per ounce for the year was $847 per ounce – seven per cent lower than in 2016. 

“The combination of increased production and lower costs and a small increase in the gold price resulted in a 14 per cent increase in profit attributable to shareholders.

“The strong operational and financial performance translated once more into very strong cash flows.  During the Year the Group generated over $24 million of cash from operations (2016: $23 million).  From these cash flows and cash resources, Blanket funded $18 million of expansion capital investment, $3.5 million of sustaining capital expenditure and repaid $1.5 million of debt; Caledonia also paid $2.9 million of dividends.         

“During the Year we made excellent progress on implementing the Investment Plan at Blanket Mine with the objective of increasing production to 80,000 ounces of gold per year by 2021.  The Central Shaft has reached a depth of 990 metres, the station for the second new haulage level has been completed and shaft sinking has re-commenced. 

“Exploration continues at Blanket with encouraging results.  In November 2017, we announced a resource upgrade which increased the gold contained in Measured and Indicated Resources by six per cent to 714,000 ounces. The gold contained in Inferred Resources increased by 47 per cent to 887,000 ounces. 

“Following the resource upgrade, we have extended the scope of the Central Shaft project by increasing the depth of the shaft by a further 250 metres to a shaft bottom depth of 1,330 metres.  The extension will allow for a further two production levels (in addition to the two new levels that were already planned) and will potentially extend Blanket’s life of mine by four years to 2031.  The shaft extension and the new production levels will cost approximately $18 million – much less than if we had done this work after the shaft had been completed and commissioned to the original target depth of 1,080 metres.  The extension of the shaft is not expected to delay the achievement of the target production of approximately 80,000 ounces per year by 2021 but it will improve operational flexibility.

“There were some significant political developments in Zimbabwe towards the end of 2017 which culminated in the appointment of the new President.  The new President has made several pronouncements regarding a relaxation in the indigenisation policy and specifically the removal of the indigenisation requirement for gold mining companies.  These pronouncements have now passed into law and accordingly, the boards of Caledonia and Blanket have agreed to implement a rights issue at Blanket to raise approximately $4 million which will be underwritten by Caledonia’s Zimbabwean subsidiary.  Blanket will use the proceeds of the rights issue to advance work on certain of its satellite properties. Assuming that Blanket’s indigenous shareholders do not subscribe for shares in accordance with their rights, it is expected that, subject to the terms of the rights issue, Caledonia’s shareholding in Blanket will increase from 49 per cent to slightly over 50 per cent. 

 “Caledonia will also evaluate the potential to buy the shareholdings in Blanket that are currently held by certain indigenous shareholders.  However, it is our intention to retain the shareholders representing employees and the local community (both of which currently hold 10 per cent each) as long term shareholders of Blanket.  Any transactions would reflect the value of the indigenous shareholders’ holdings in Blanket after deducting the value of their outstanding facilitation loans and would be subject to a mutually agreed valuation of the holdings in Blanket.

“I wholeheartedly welcome the change in legislation which means that Caledonia can commit new capital so that Blanket can commence exploration and evaluations of additional projects in Zimbabwe.  If this investment is successful it will benefit all stakeholders, including Blanket’s indigenous shareholders, future employees on the new projects, the communities around the new projects and the government of Zimbabwe which would benefit from increased royalty and tax receipts and greater inflows of foreign exchange arising from increased gold production.   

“We are at a very exciting point in our development. At our current production level of over 55,000 ounces of gold per annum we are already highly cash generative. For the next two years, the bulk of the cash generation will be deployed to the Investment Plan at Blanket which we are confident will further increase cash flows as we increase production to 80,000 ounces of gold by 2021.  Once the Investment Plan is completed towards the end of 2020, we expect to have substantial free cash flows to deploy elsewhere.  Against this background, there are very encouraging political developments in Zimbabwe which we are optimistic will create new investment opportunities.”

Shareholder Conference Call

A presentation of the 2017 results and outlook for Caledonia is available on Caledonia’s website (www.caledoniamining.com). Management will host a conference call at 1500 GMT on March 27 2018.

Details for the call are as follows:

Date: March 27, 2018

Time: 1500 London, 1600 Johannesburg, 1600 Zurich and Frankfurt, 1000 Toronto and New York

For further information please contact:

Caledonia Mining Corporation Plc

Mark Learmonth Tel: +44 1534 679 802

Maurice Mason 

WH Ireland

Adrian Hadden/Ed Allsopp Tel: +44 20 7220 1751

Blytheweigh

Tim Blythe/Camilla Horsfall/Megan Ray  

Chief Executive’s Report

Safety

Regrettably, there were two fatal accidents in Year and a third fatal accident occurred on February 23, 2018. The directors and management of Caledonia and Blanket express their sincere condolences to the families and colleagues of each of the deceased. Management has provided the necessary assistance to the Ministry of Mines Inspectorate Department in its enquiries into this incident. Caledonia takes the safety of its employees very seriously and accordingly, measures have been taken to re-inforce adherence to prescribed safety procedures through increased training activities.

Record production

16,425 ounces of gold were produced during the Quarter, 14 per cent more than the 14,396 ounces produced in the third quarter of 2017 (the “preceding quarter”), which was itself a new production record. 56,133 ounces of gold were produced in the Year, 11.5 per cent more than in 2016. The increased production was due to higher tonnes mined, as the remedial measures that were taken in previous quarters to address logistical constraints bore fruit and improved grades, which resulted from increased mining of higher grade areas as mine flexibility continues to improve.

Resource upgrade

On November 2, 2017 the Company announced that total Measured and Indicated gold ounces at Blanket Mine had increased by six per cent from 671,000 ounces in December 2016 to 714,000 ounces as at August 31, 2017. Total Measured and Indicated resources at August 31, 2017 were 5.62 million tonnes at a grade of 3.95 grammes per tonne (“g/t”). Inferred gold resources at Blanket increased by 47 per cent from 604,000 ounces in December 2016 to 887,000 ounces at August 31, 2017. Total Inferred resources at August 31, 2017 were 5.53 million tonnes at a grade of 4.99g/t.

The update resulted in a modest decline in the average grade of the resources in the Indicated category as a result of additional infill drilling data although the average resource grade remains well above the current mill feed grade. Caledonia expects the mined grade to trend upwards over time as higher-grade resources are accessed at depth. This resource update marked the sixth successive year of sustained resource growth at Blanket. Blanket’s resources (both in terms of Measured & Indicated resources and Inferred resources) have grown by approximately 69 per cent since 2011 despite mining over 250,000 ounces over this period.

Extension of the Central Shaft Project at Blanket Mine

Following the announcement of the updated resource statement on November 2, 2017, on November 10, 2017 Caledonia announced that it plans to extend the depth of the Central Shaft which is currently under construction at Blanket by a further 250 metres to a shaft bottom depth of 1,330 metres. The extension of the Central Shaft will add two further production levels on 34 level at 1,110 metres and on 38 level at 1,230 metres in addition to the two levels that are already planned on 26 level (870 metres) and 30 level (990 metres). It is expected that the extended shaft will be fully commissioned by the end of the first quarter of 2020.

The extension of the shaft and associated capital development of additional production levels will cost approximately $18 million which will be funded by Blanket’s internal cash generation. The additional capital investment is not expected to have any effect on the continuation of Caledonia’s existing dividend.

The addition of two further production levels will provide access to the Indicated and Inferred resources below 30 level and potentially increase Blanket’s projected life of mine by a further four years to 2031.

The extension of the Central Shaft before it has been completed, equipped and commissioned is understood to be significantly cheaper, quicker and less disruptive than a subsequent extension after commissioning.

Caledonia has also initiated a mid-shaft loading system at Blanket using the existing Central Shaft infrastructure to handle development waste. This is expected to improve Blanket’s waste handling capacity and alleviate pressure on Number 4 Shaft which in turn should have a positive effect on both production flexibility and horizontal development.

The extension of the Central Shaft and the introduction of mid-shaft loading is expected to extend the completion date for Central Shaft from late 2019 until early 2020, but should not delay the target production of 80,000 ounces of gold per year by 2021.

Dividend Policy

On July 4, 2017, following the consolidation on June 26, 2017 of the Company’s shares, the Company announced an increased quarterly dividend of 6.875 cents per share which was paid on July 28, 2017 and further quarterly dividends of the same amount were paid on October 27, 2017 and January 26, 2018. The dividend of 6.875 cents per share effectively maintains the dividend at the previous level of 1.375 cents per share, after adjusting for the effect of the one-for-five share consolidation. The quarterly dividend of 6.875 cents per quarter is Caledonia’s current dividend policy which it is envisaged will be maintained.

Strategy and Outlook

Caledonia’s strategic focus continues to be the implementation of the Investment Plan at Blanket, which was announced in November 2014 and has been revised as discussed above to reflect the recent resource upgrade and deepening of the Central Shaft. Caledonia’s board and management team believe that the successful implementation of the Investment Plan is in the best interests of all stakeholders because it is expected to result in increased production, reduced operating costs and increased flexibility to undertake further exploration and development, thereby safeguarding and enhancing Blanket’s long term future.

Changes to the Indigenisation Legislation

Pronouncements from the Zimbabwe Government following the appointment of the new President in late 2017 announced a relaxation in the indigenisation policy which, amongst other things, includes the removal of an indigenisation requirement for gold mining companies. These pronouncements were been passed into law in March, 2018. In light of the changed legislation, the Blanket (which expression in this paragraph means the company owning Blanket Mine) and Caledonia boards have agreed to implement a transaction which is expected to increase Caledonia’s shareholding in Blanket from 49 per cent to approximately 51 per cent. Caledonia will also evaluate the potential to buy back the shareholdings in Blanket that are currently held by certain indigenous shareholders. However, it is our intention to retain the Blanket Employee Trust Services (Private) Limited and Gwanda Community Share Ownership Trust (both of which currently hold 10 per cent of Blanket each) as long term shareholders of Blanket. Any transactions would reflect the value of the indigenous shareholders’ holdings in Blanket after deducting the value of their outstanding facilitation loans. At this stage there is no certainty that agreement will be reached on transactions in respect of any shareholdings.

Note: This announcement contains information which, prior to its disclosure by this announcement, was inside information for the purposes of the Market Abuse Regulation.

Cautionary Note Concerning Forward-Looking Information

Information and statements contained in this news release that are not historical facts are “forward-looking information” within the meaning of applicable securities legislation that involve risks and uncertainties relating, but not limited to Caledonia’s current expectations, intentions, plans, and beliefs. Forward-looking information can often be identified by forward-looking words such as “anticipate”, “believe”, “expect”, “goal”, “plan”, “target”, “intend”, “estimate”, “could”, “should”, “may” and “will” or the negative of these terms or similar words suggesting future outcomes, or other expectations, beliefs, plans, objectives, assumptions, intentions or statements about future events or performance. Examples of forward-looking information in this news release include: production guidance, estimates of future/targeted production rates, and our plans and timing regarding further exploration and drilling and development. This forwardlooking information is based, in part, on assumptions and factors that may change or prove to be incorrect, thus causing actual results, performance or achievements to be materially different from those expressed or implied by forward-looking information. Such factors and assumptions include, but are not limited to: failure to establish estimated resources and reserves, the grade and recovery of ore which is mined varying from estimates, success of future exploration and drilling programs, reliability of drilling, sampling and assay data, assumptions regarding the representativeness of mineralization being inaccurate, success of planned metallurgical test-work, capital and operating costs varying significantly from estimates, delays in obtaining or failures to obtain required governmental, environmental or other project approvals, inflation, changes in exchange rates, fluctuations in commodity prices, delays in the development of projects and other factors. Security holders, potential security holders and prospective investors should be aware that these statements are subject to known and unknown risks, uncertainties and other factors that could cause actual results to differ materially from those suggested by the forward-looking statements. Such factors include, but are not limited to: risks relating to estimates of mineral reserves and mineral resources proving to be inaccurate, fluctuations in gold price, risks and hazards associated with the business of mineral exploration, development and mining, risks relating to the credit worthiness or financial condition of suppliers, refiners and other parties with whom the Company does business; inadequate insurance, or inability to obtain insurance, to cover these risks and hazards, employee relations; relationships with and claims by local communities and indigenous populations; political risk; availability and increasing costs associated with mining inputs and labour; the speculative nature of mineral exploration and development, including the risks of obtaining or maintaining necessary licenses and permits, diminishing quantities or grades of mineral reserves as mining occurs; global financial condition, the actual results of current exploration activities, changes to conclusions of economic evaluations, and changes in project parameters to deal with unanticipated economic or other factors, risks of increased capital and operating costs, environmental, safety or regulatory risks, expropriation, the Company’s title to properties including ownership thereof, increased competition in the mining industry for properties, equipment, qualified personnel and their costs, risks relating to the uncertainty of timing of events including targeted production rate increase and currency fluctuations. Shareholders are cautioned not to place undue reliance on forward-looking information. By its nature, forward-looking information involves numerous assumptions, inherent risks and uncertainties, both general and specific, that contribute to the possibility that the predictions, forecasts, projections and various future events will not occur. Caledonia undertakes no obligation to update publicly or otherwise revise any forward-looking information whether as a result of new information, future events or other such factors which affect this information, except as required by law.

Firmenkontakt und Herausgeber der Meldung:

Swiss Resource Capital AG
Poststrasse 1
CH9100 Herisau
Telefon: +41 (71) 354-8501
Telefax: +41 (71) 560-4271
http://www.resource-capital.ch

Ansprechpartner:
Jochen Staiger
CEO
Telefon: +41 (71) 3548501
E-Mail: js@resource-capital.ch
Für die oben stehende Pressemitteilung ist allein der jeweils angegebene Herausgeber (siehe Firmenkontakt oben) verantwortlich. Dieser ist in der Regel auch Urheber des Pressetextes, sowie der angehängten Bild-, Ton-, Video-, Medien- und Informationsmaterialien. Die United News Network GmbH übernimmt keine Haftung für die Korrektheit oder Vollständigkeit der dargestellten Meldung. Auch bei Übertragungsfehlern oder anderen Störungen haftet sie nur im Fall von Vorsatz oder grober Fahrlässigkeit. Die Nutzung von hier archivierten Informationen zur Eigeninformation und redaktionellen Weiterverarbeitung ist in der Regel kostenfrei. Bitte klären Sie vor einer Weiterverwendung urheberrechtliche Fragen mit dem angegebenen Herausgeber. Eine systematische Speicherung dieser Daten sowie die Verwendung auch von Teilen dieses Datenbankwerks sind nur mit schriftlicher Genehmigung durch die United News Network GmbH gestattet.