Revival Gold Inc. (TSXV: RVG, OTCQX: RVLGF) (“Revival Gold” or the “Company” – https://www.commodity-tv.com/ondemand/companies/profil/revival-gold-inc/), is pleased to provide an update on the status of work on a Prefeasibility Study (“PFS”) for the Beartrack-Arnett Gold Project (“Beartrack-Arnett”) located in Lemhi County, Idaho, USA.

PFS Team and Schedule

  • Revival Gold has appointed Kappes Cassiday Associates (“KCA”) as the lead PFS consultant focused on metallurgy, infrastructure design and overall study economic analysis with Independent Mining Consultants Inc. (“IMC”) engaged on mineral resources and to develop PFS-level open pit designs and mine plans. KCA and IMC are US-based experts in gold heap leach mine design and operations.
  • Technical studies in support of the PFS (see below) are progressing on track; however, with the shift in overall project management and mine planning from the Company’s previous engineering consultants to KCA and IMC, respectively, completion of the PFS will be deferred to 2023. This will, however, provide time for Revival Gold to incorporate 2022’s drilling into the PFS which should improve results. PFS completion is expected mid-2023.

Technical Studies

  • Comprehensive metallurgical work has been completed on nine 180-day column leach tests by SGS Lakefield with results indicating average gold recoveries of 82% relative to the cyanide soluble gold assay for Beartrack and 92% relative to total fire assay gold for Arnett. All column testing was completed on 38 mm (1.5 inch) crush size material. Together with existing data, these results provide further confidence in Beartrack-Arnett heap leach recovery assumptions going into the PFS.
  • Two PFS-level geotechnical characterization studies have been completed by Wood plc. The open pit geotechnical study provides pit slope design criteria and identifies opportunities to further steepen (improve) pit slopes with enhanced blasting practices, while the infrastructure geotechnical study characterizes the foundation conditions for the heap leach pad, waste rock dumps, haul roads and other surface infrastructure.
  • PFS-level waste rock management design and water management studies are ongoing at ALS Limited on 72 rock samples representative of Arnett waste rock. A preliminary assessment of the results has identified that most samples have generally undetectable sulfide sulphur content (<0.01%) with several samples identified with low but measurable sulphide sulphur content (up to 0.1%).
  • Idaho Power Company (“IPCo”) is advancing a study to assess upgrades required to the existing 69 kV service to site to support the PFS. The IPCo upgrades are anticipated to include substation infrastructure improvements, increasing the conductor gauge, and possibly replacing some power poles.

“We are delighted to welcome KCA and IMC as principal consultants on the Beartrack-Arnett PFS”, said Hugh Agro, President and CEO. “These firms add a wealth of recent and relevant experience in western US heap leach design and operation. Although the change in principal consultants will result in a scheduling delay, the upside to this delay is that it provides an opportunity to complete additional drilling this year which should enhance the mineral resource and improve PFS results”, added Agro.

Qualified Persons

John P.W. Meyer, P.Eng., Vice President, Engineering & Development is the Company’s designated Qualified Person for this news release within the meaning of National Instrument 43‑101 Standards of Disclosure for Mineral Projects and has reviewed and approved its scientific and technical content.

About Revival Gold Inc.

Revival Gold Inc. is a growth-focused gold exploration and development company. The Company is advancing the Beartrack-Arnett Gold Project located in Idaho, USA.

Beartrack-Arnett is the largest past-producing gold mine in Idaho.  Engineering work has been initiated on a Preliminary Feasibility Study (“PFS”) for the potential restart of heap leach operations. Meanwhile, exploration continues, focused on expanding the 2022 Indicated Mineral Resource of 65.0 million tonnes at 1.01 g/t gold containing 2.11 million ounces of gold and Inferred Mineral Resource of 46.2 million tonnes at 1.31 g/t gold containing 1.94 million ounces of gold (see Revival Gold NI-43-101 Technical Report dated July 13th 2022, for further details).  The mineralized trend at Beartrack extends for over five kilometers and is open on strike and at depth. Mineralization at Arnett is open in all directions.

Revival Gold has approximately 86.9 million shares outstanding and an estimated cash balance of C$7.1 million as of June 30th, 2022. All figures in this news release are in metric units and in $US unless stated otherwise. Additional disclosure including the Company’s financial statements, technical reports, news releases and other information can be obtained at www.revival-gold.com or on SEDAR at www.sedar.com.

For further information, please contact:

Hugh Agro, President & CEO or Melisa Armand, Manager, Investor Relations
Telephone: (416) 366-4100 or Email: info@revival-gold.com

In Europe:
Swiss Resource Capital AG
Jochen Staiger
info@resource-capital.ch
www.resource-capital.ch

Cautionary Statement

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release.

This News Release includes certain "forward-looking statements" which are not comprised of historical facts. Forward-looking statements include estimates and statements that describe the Company’s future plans, objectives or goals, including words to the effect that the Company or management expects a stated condition or result to occur. Forward-looking statements may be identified by such terms as “believes”, “anticipates”, “expects”, “estimates”, “may”, “could”, “would”, “will”, or “plan”. Since forward-looking statements are based on assumptions and address future events and conditions, by their very nature they involve inherent risks and uncertainties. Although these statements are based on information currently available to the Company, the Company provides no assurance that actual results will meet management’s expectations. Risks, uncertainties, and other factors involved with forward-looking information could cause actual events, results, performance, prospects, and opportunities to differ materially from those expressed or implied by such forward-looking information. Forward looking information in this news release includes, but is not limited to, the Company’s objectives, goals or future plans, statements, exploration results, potential mineralization, the estimation of mineral resources, exploration and mine development plans, timing of the commencement of operations and estimates of market conditions. Factors that could cause actual results to differ materially from such forward-looking information include, but are not limited to failure to identify mineral resources, failure to convert estimated mineral resources to reserves, the inability to complete a feasibility study which recommends a production decision, the preliminary nature of metallurgical test results, delays in obtaining or failures to obtain required governmental, environmental or other project approvals, political risks, uncertainties relating to the availability and costs of financing needed in the future, changes in equity markets, inflation, changes in exchange rates, fluctuations in commodity prices, delays in the development of projects, capital, operating and reclamation costs varying significantly from estimates and the other risks involved in the mineral exploration and development industry, an inability to predict and counteract the effects of COVID-19 on the business of the Company, including but not limited to the effects of COVID-19 on the price of commodities, capital market conditions, restriction on labour and international travel and supply chains, and those risks set out in the Company’s public documents filed on SEDAR. Although the Company believes that the assumptions and factors used in preparing the forward-looking information in this news release are reasonable, undue reliance should not be placed on such information, which only applies as of the date of this news release, and no assurance can be given that such events will occur in the disclosed time frames or at all. The Company disclaims any intention or obligation to update or revise any forward-looking information, whether as a result of new information, future events or otherwise, other than as required by law.

Firmenkontakt und Herausgeber der Meldung:

Swiss Resource Capital AG
Poststrasse 1
CH9100 Herisau
Telefon: +41 (71) 354-8501
Telefax: +41 (71) 560-4271
http://www.resource-capital.ch

Ansprechpartner:
Jochen Staiger
CEO
Telefon: +41 (71) 3548501
E-Mail: js@resource-capital.ch
Für die oben stehende Pressemitteilung ist allein der jeweils angegebene Herausgeber (siehe Firmenkontakt oben) verantwortlich. Dieser ist in der Regel auch Urheber des Pressetextes, sowie der angehängten Bild-, Ton-, Video-, Medien- und Informationsmaterialien. Die United News Network GmbH übernimmt keine Haftung für die Korrektheit oder Vollständigkeit der dargestellten Meldung. Auch bei Übertragungsfehlern oder anderen Störungen haftet sie nur im Fall von Vorsatz oder grober Fahrlässigkeit. Die Nutzung von hier archivierten Informationen zur Eigeninformation und redaktionellen Weiterverarbeitung ist in der Regel kostenfrei. Bitte klären Sie vor einer Weiterverwendung urheberrechtliche Fragen mit dem angegebenen Herausgeber. Eine systematische Speicherung dieser Daten sowie die Verwendung auch von Teilen dieses Datenbankwerks sind nur mit schriftlicher Genehmigung durch die United News Network GmbH gestattet.

counterpixel